Changjiang Unit 4 control room brought into operation; Phase II units 3 and 4 nearing commissioning timeline
Unit 4 commissioning milestone
A ceremony on 31 July marked the launch of operation of the main control room for Changjiang unit 4, according to China National Nuclear Corporation, which said it “marked a new stage in the commissioning and operation of unit 4.” The ceremony also referenced full commencement of operation and duty shifts in the main control room as an important milestone tied to project construction efforts across multiple participants and company departments.
Changjiang Phase II includes two Hualong One reactors, with unit 3 and unit 4 moving through civil works and commissioning steps that now include the control-room operating phase.
Construction status and commissioning progress for Phase II
First concrete for the unit 3 nuclear island base slab was poured in March 2021, followed by the unit 4 base slab in December 2021.
Changjiang unit 3 reached first criticality on 10 July and was connected to the grid on 1 August. Both Phase II units are scheduled to be fully operational in early 2027.
The Changjiang Phase II - units 3 and 4 - project is described as representing a total estimated investment of CNY40 billion (USD5.9 billion), with China Huaneng holding a 51% share in the project.
SMR work at the same site
Beyond the Phase II Hualong One units, the Changjiang nuclear site is also home to two operating CNP-600 pressurised water reactors, Changjiang 1 and 2, which entered commercial operation in 2015 and 2016.
In 2021, China National Nuclear Corporation began construction of a demonstration ACP100 small modular reactor at the site. The multi-purpose 125 MWe pressurised water design—also referred to as the Linglong One—covers electricity generation as well as heating, steam production, or seawater desalination, and it is currently undergoing pre-commissioning tests.